Highway 400 bridge connecting Harvie and Big Bay Point roads expected to be ready for traffic next summer

Businesses are reopening as the COVID-19 lockdown is gradually lifted. Let your customers, new and current, know you are open for business. Get noticed, build your brand and audience with Devine Media Service. Display your ad and/or promotion, have it proactively promoted through social media feeds, have those feeds managed, and support local journalism, for one, affordable and inclusive price

The east and west sides of Barrie divided by Highway 400 will be more connected next summer, as the bridge joining Harvie and Big Bay Point roads is scheduled to open.
All roadwork on the east side of the bridge will be complete and open to traffic by late October. All roadwork west of the Harvie Road reservoir is wrapping up as well, and Harvie will reopen by the end of this month.
The project is near completion and had an anticipated completion date of early November. Construction has progressed well, but the nature of remaining work, combined with uncertain weather conditions, makes the opening of the bridge by the end of October unlikely.
The east side of the bridge will be complete by late October, but the west side of the bridge requires further work, including bringing in fill to build up the embankment to meet the bridge, water main installation and asphalt work. The project contractor has made the decision to shut down operations for the winter at the end of October. While working into November and December may be possible, dependent on weather, there is work that can’t be completed in low temperatures or under wet conditions. Work will be shut down over the winter months and will restart in spring 2021.
It’s estimated that the entire project will be complete by late June 2021. This major $76 million project has been carefully designed and constructed over the last four years to help reduce traffic congestion in Barrie’s south end. This final work will ensure that the project is completely ready for public use, including active transportation options, by next year.
Over the last 10 months, the following work has taken place on this project:​​
• construction of the centre pier, and the east and west abutments
• formwork and reinforcing steel for the bridge
• delivery and placement of fill material for the east and west embankments
• installation of storm sewers and water-mains
• installation of 26 bridge girders and concrete pouring for the bridge deck
• paving of the new road surfaces and pouring of concrete sidewalks
When complete, the bridge will have five lanes for vehicle traffic, two separate lanes for bicycles and two sidewalks for pedestrians. Visit barrie.ca/roadwork for more information.

Share